MCRP 3-40D.6 — Construction Project Management Ntrp 4-04.2.5

MCRP 3-40D.6 governs construction project management methods, procedures, and formats for military engineer units.

Search MCRP 3-40D.6

  • Publication number: MCRP 3-40D.6
  • Title: CONSTRUCTION PROJECT MANAGEMENT NTRP 4-04.2.5
  • Date: 1 Dec 2012
  • Proponent: 03000 Operations & Readiness
  • Status: Current

View MCRP 3-40D.6 on armypubs.army.mil


MCRP 3-40D.6 covers preliminary planning, project organization, scheduling, quality control, safety, and environmental protection. It requires project documentation, testing plans and logs, current schedules, safety precautions, and maintained as-built records.

Applies to: This publication is a multiservice publication that provides uniform guidance to describe common methods, procedures, and formats for all aspects of construction project management at the operational unit level required to successfully plan, schedule, and execute a construction project by military engineer units.

Topics covered

  • Preliminary construction planning
  • Construction activity numbering
  • Level III Gantt charts
  • Quality control testing
  • Jobsite safety
  • Environmental protection
  • Tool management
  • As-built record drawings

Questions and answers

How are construction activities documented?

Each construction activity is documented using a CAS sheet. (paragraph 6)

How are activities listed on a Level III Gantt chart?

List each construction activity in order by its ES date. (paragraph 1)

What must construction projects have for safety?

All construction projects have safety considerations requiring an approved plan. (paragraph 1-5)

How often are as-built drawings reviewed?

The project manager and QC manager review these drawings every 2 weeks to ensure they are current. (paragraph 1-5)

How much material can be stored at a project site?

No more than 2 weeks of material is stored at the project site. (paragraph 7)