MCRP 3-40D.6 governs construction project management methods, procedures, and formats for military engineer units.
View MCRP 3-40D.6 on armypubs.army.mil
MCRP 3-40D.6 covers preliminary planning, project organization, scheduling, quality control, safety, and environmental protection. It requires project documentation, testing plans and logs, current schedules, safety precautions, and maintained as-built records.
Applies to: This publication is a multiservice publication that provides uniform guidance to describe common methods, procedures, and formats for all aspects of construction project management at the operational unit level required to successfully plan, schedule, and execute a construction project by military engineer units.
Each construction activity is documented using a CAS sheet. (paragraph 6)
List each construction activity in order by its ES date. (paragraph 1)
All construction projects have safety considerations requiring an approved plan. (paragraph 1-5)
The project manager and QC manager review these drawings every 2 weeks to ensure they are current. (paragraph 1-5)
No more than 2 weeks of material is stored at the project site. (paragraph 7)