MCO 7100.13 governs the development and consolidation of O&M MC budget estimates for Marine Corps Prepositioning Programs.
View MCO 7100.13 on armypubs.army.mil
The publication covers POM development, budget submissions, funding adjustments, exercise cost estimates, phasing plans, and quarterly assessments. It requires supporting documentation for annual budget estimates and establishes requirements for MCPP-N burden sharing.
Applies to: This Order focuses on developing O&M MC budget estimates for MPF and MCPP-N program support, sustainment, and exercise requirements as determined by program managers and validated by their respective commanders.
Annual budget estimates submitted by stakeholders must be submitted with supporting documentation as outlined throughout this order and SUSPEB guidance in order to validate service level budget estimates and defend PR/POM submissions. (paragraph 4)
Phasing plans are developed prior to the beginning of each FY to show by month how much funding is required. (paragraph 8)
PEBFT provides an Exercise Summary Cost Worksheet for each exercise that forecasts the exercise costs by funding category, sub category and OC-SOC. (paragraph 7)
MARFORs will utilize the OPBUD distribution entered into PEBFT and assign their available funding to each exercise based on their priority. (paragraph 8)
The actual annual amount budgeted towards MCPP-N by either the U.S. or Norway does not have to match the agreed upon Cost Sharing amount, however it must not be less than the agreed upon Cost Sharing amount. (paragraph 3)