MCO 11000.5 — Facilities Sustainment, Restoration And Modernization Program

MCO 11000.5 governs the planning, programming, budgeting, and execution of the Marine Corps Facilities Sustainment, Restoration and Modernization Program.

Search MCO 11000.5

  • Publication number: MCO 11000.5
  • Title: FACILITIES SUSTAINMENT, RESTORATION AND MODERNIZATION PROGRAM
  • Date: 3 Jun 2016
  • Proponent: 11000 Facilities & Activities Ashore
  • Status: New

View MCO 11000.5 on armypubs.army.mil


It covers real property maintenance, repair, minor construction, demolition, energy investment, project prioritization, and funding approval levels. It establishes requirements for project justification, technical solutions, cost estimates, economic analysis, and contract modifications.

Applies to: Service Level Training Installations (SLTIs) under Marine Corps Training and Education Command (TECOM), per reference (d), are included under the term installations and are supported by their respective Marine Corps Installations Command (MCICOM) Regional Command for all FSRM requirements and coordination.

Topics covered

  • Facilities Sustainment, Restoration and Modernization
  • Real property inventory
  • FSRM funded costs
  • Funding approval levels
  • Project prioritization
  • Project justification
  • Technical solutions
  • Contract modifications

Questions and answers

What requirements are included in the FSRM program?

FSRM requirements include maintenance, repair, minor construction, and demolition of all real property and are funded annually. (paragraph 1)

What does real property exclude?

Real property does not include personal property (weapons systems and other military equipment). (paragraph 1)

How must an FSRM project be justified?

Each project must be justified on the basis of mission, life-cycle economics, health and safety, quality of life, or some combination of the above criteria. (paragraph 3)

Can an installation proceed with a change order above the authorized contingency ceiling?

The Installation cannot proceed with the change order until the ADC LF/COMMCICOM approves this request and a new contingency ceiling has been established. (paragraph 3)