WR-ALCI21-122 governs the maintenance, distribution, and control of engineering design data within the Warner Robins Air Logistics Complex.
View WR-ALCI21-122 on armypubs.army.mil
The publication covers engineering design data for routed items, locally manufactured items, temporary work requests, project modification and repair workloads, and contractor-supplied data. It requires currency checks, authorized-use annotations, controlled distribution, and specified data disposition.
Applies to: It applies to all WR-ALC personnel performing work to support a production realization or verification process.
The ATEAM is the primary method used by personnel who require engineering design data. (paragraph 1)
Engineering data ordered for use by WR-ALC will not be released in any manner, or by any means, to a foreign national/government/contractor. (paragraph 1)
Unless otherwise specified by the planning organization, all personnel will ensure engineering design data is destroyed or returned to planning immediately after each individual work request is completed. (paragraph 1)
If engineering design data was last IET-stamped 90 or more days prior to the date of work request, the currency of the engineering design data must be verified with the source/provider or cognizant engineering authority and documented.
Production supervisors ensure all engineering design data is current and only engineering design data required in support of active work orders is located in the production areas.