PACAFPAM24-1 — Airlift Planning Guide

PACAFPAM24-1 governs airlift request planning and submission for Pacific Air Forces, including SAAM requests, validation, approval, and pricing.

Search PACAFPAM24-1

  • Publication number: PACAFPAM24-1
  • Title: AIRLIFT PLANNING GUIDE
  • Date: 2022-03-08

View PACAFPAM24-1 on armypubs.army.mil


The publication covers unit, base, MAJCOM, USTRANSCOM, and theater airlift functions, along with load plans, hazardous materials, diplomatic clearances, and SAAM processing. It requires specific request formats, submission timelines, validation steps, and coordination through the SAAM Request System.

Applies to: This publication does not apply to the Air National Guard (ANG) or their units.

Topics covered

  • Airlift requests
  • SAAM Request System
  • Load plans
  • Hazardous materials
  • Diplomatic clearance worksheets
  • Airlift pricing
  • Minimum activity rates

Questions and answers

What form and documents are required for a SAAM request?

The unit is required to accomplish the basic special assignment airlift mission (SAAM) request using the DD Form 1249, Airlift Request – SAAM or Joint Chiefs of Staff (JCS) Exercise format and an aircraft load plan. (paragraph 1)

Where must airlift requests be submitted, and what format is required?

All airlift requests must be submitted in SRS using the proper format IAW DTR 4500.9R Part II, Appendix Q. (paragraph 24-114)

When is the 10 percent airlift discount allocated?

A 10 percent discount is allocated if USTRANSCOM approves a SAAM request no later than 30 days prior to execution date. (paragraph 24-114)

What is the minimum activity rate for the C-17?

Please note the MAR for the C-17 is 4 hours as opposed to the 2 hour MAR with all other AMC aircraft. (paragraph 24-114)