DAFPD99-1 — Test And Evaluation

DAFPD99-1 governs Air Force and Space Force test and evaluation policy across acquisition, development, production, fielding, and sustainment.

Search DAFPD99-1

  • Publication number: DAFPD99-1
  • Title: TEST AND EVALUATION
  • Date: 2025-06-24

View DAFPD99-1 on armypubs.army.mil


DAFPD99-1 addresses developmental, operational, integrated, and live-fire testing, including test infrastructure and weapon system evaluation. It requires objective testing, early risk reduction, verified modeling and simulation tools, and intelligence-informed planning.

Applies to: This DAFPD applies to all Regular Air Force, United States Space Force (USSF), Air Force Reserve, Air National Guard, and other Department of the Air Force (DAF) individuals or organizations that plan and/or conduct Test and Evaluation (T&E) activities.

Topics covered

  • Developmental testing and evaluation
  • Operational testing and evaluation
  • Integrated testing
  • Live-fire testing
  • Test infrastructure
  • Weapon System Evaluation Program
  • Modeling and simulation tools
  • Threat environment assessment

Questions and answers

What information does test and evaluation provide?

T&E provides detailed information on the progress of the system design, compliance with contractual requirements, combat capability, and the ability to be sustained once fielded. (paragraph 1)

What is developmental testing and evaluation used for?

DT&E is conducted throughout the acquisition and sustainment processes to assist engineering design and development, verify developer compliance with contractual requirements, and provide data for use by operational test organizations to verify operational suitability, effectiveness, survivability, and lethality, as applicable, of the system in development. (paragraph 1)

What does operational testing and evaluation assess?

OT&E is an independent assessment of the operational effectiveness, suitability, survivability, and lethality, as applicable, of the system under development. (paragraph 1)

How must integrated testing be conducted?

Integrated testing is the collaborative planning and execution of developmental and operational test activities and events to provide shared data. (paragraph 1)

How is live-fire test and evaluation treated?

Live-fire T&E shall be treated as an integrated test activity to include both developmental and operational testing. (paragraph 1)