AFMCI23-110 governs post-award part verification and approval requirements, including first article and other testing.

Search AFMCI23-110

  • Publication number: AFMCI23-110
  • Title: POST-AWARD PART VERIFICATION AND APPROVAL
  • Date: 2024-01-31

View AFMCI23-110 on armypubs.army.mil


AFMCI23-110 covers first article testing, production part approval, specialized testing, and form, fit, and function testing. It defines pre-solicitation, solicitation, and post-contract-award phases and requires process tracking and monthly status reports.

Applies to: This instruction applies to Regular Air Force and United States Space Force units utilizing first article testing, production part approval, specialized inspection and testing, FFF and other testing requirements for post award verification, including foreign military sales.

Topics covered

  • First article testing
  • Production part approval
  • Specialized inspection and testing
  • Form, fit, and function testing
  • Post-award verification phases
  • Test status reporting

Questions and answers

When can the expedited post-award verification process be used?

An expedited 30 calendar day process will be established at each field activity for high priority procurements. (paragraph 1)

What must a first article solicitation or purchase document contain?

Any first article solicitation or purchase document must contain detailed technical requirements and adequate quality assurance provisions to ensure that the contractor is capable of furnishing or manufacturing the item. (paragraph 1)

What is first article inspection used to verify?

Use first article inspection to verify that the contractor can provide an item manufactured to a previously qualified design. (paragraph 1)

When may first article inspection be performed at a contractor facility?

First article inspection may be performed at an approved contractor facility when there are no government unique testing requirements, and it is in the best interest of the government. (paragraph 1)

What does the post-contract-award phase end with?

The Post Contract Award phase begins with contract award and ends with the acceptance of compliant product from the manufacturer.