AFMCI21-126 — Temporary 2 (t-2) Modification Of Aerospace Vehicles

AFMCI21-126 governs the management, control, documentation, and processing of Temporary 2 modifications to aerospace vehicles.

Search AFMCI21-126

  • Publication number: AFMCI21-126
  • Title: TEMPORARY 2 (T-2) MODIFICATION OF AEROSPACE VEHICLES
  • Date: 2020-05-15

View AFMCI21-126 on armypubs.army.mil


It covers T-2 modification classification, approval, design reviews, safety determinations, demodification, flight releases, and revalidation. It also addresses contracted modifications, lease or loan agreements, funding reimbursement, local supplements, and prescribed forms.

Applies to: This instruction does not apply to the Air National Guard or US Air Force Reserve units and members.

Topics covered

  • Temporary 2 modifications
  • Uncertified external and internal stores
  • Modification classification
  • Independent Modification Review
  • Safety of Flight determinations
  • Demodification plans
  • Flight releases
  • Modification revalidation

Questions and answers

How long can a T-2 modification remain installed?

T-2 modifications may be installed only for the duration of the flight test program unless stated in the demodification plan or an extension is approved by the Modification Engineering Authority (MEA) (reference paragraph 12.2). (paragraph 1)

What classifications apply to T-2 modifications?

All T-2 modifications, to include hardware/software, will be classified as either Major or Minor. (paragraph 5)

When is an Independent Modification Review required?

All Major T-2 aircraft modifications require an Independent Modification Review (IMR) by the responsible SPM. (paragraph 6)

How long may a temporary flight release be issued?

When a final flight release cannot be issued (e.g., an incomplete modification/demodification not affecting flight safety or a program requirement), then an AFMC Form 243 of up to 180 days may be issued by the responsible CCB authority.

What happens if the SPM does not concur with revalidation?

In the event that the SPM does not concur, the test article will be fully demodified and the organization funding the modification will be responsible for funding the demodification.