AFMCI21-118 governs AMREP data management, weapon-system reporting, aircraft scheduling, and depot maintenance metrics.
View AFMCI21-118 on armypubs.army.mil
It defines job designator codes, flow-day and out-date measures, extension dates, completion performance, and reporting requirements. It requires accurate AMREP status updates, timely aircraft reporting, and maintenance of current schedule data.
Applies to: This instruction applies to organic (ORG), contract (CON), Organic Field Team (OFT), Contract Field Team (CFT), Depot Maintenance Inter-Service Agreement, and partnership activities; it outlines aircraft metrics definitions and reporting requirements.
AMREP module data is used to measure overall AFMC weapon system support. (paragraph 1)
Aircraft possessed by AFMC undergoing depot-level inspections, repairs, or modifications at an Air Logistics Complex (ALC), field location, contractor, or transitory commercial facility will be reported in the AMREP module. (paragraph 5)
All aircraft must report as received (Received Date on an open AMREP module record) in the AMREP module within three (3) workdays after the arrival of the aircraft at the Repair Activity unless specified in a special agreement between the PM/PSM, Repair Activity, and possessing/assigned MAJCOM. (paragraph 5)
Aircraft status changes (e.g., In-work, Original Out Date/Revised Out Date /Forecast Out Date, schedule changes, delays, completions, deliveries, remarks) shall be made no later than one business day from date of actual occurrence. (paragraph 5)
First Extension End Date is calculated as 45% of the Original Flow Days. (paragraph 3)