AFI32-1023 — Designing And Constructing Military Construction Projects

AFI32-1023 governs the design and construction of real property supporting the Air Force mission worldwide.

Search AFI32-1023

  • Publication number: AFI32-1023
  • Title: DESIGNING AND CONSTRUCTING MILITARY CONSTRUCTION PROJECTS
  • Date: 2020-12-23

View AFI32-1023 on armypubs.army.mil


AFI32-1023 addresses military construction funding, program execution, installation development planning, district plans, and facility standards. It requires coordination and approval for project siting changes and establishes oversight roles for MILCON financial management and execution.

Applies to: This AFI applies to all military construction projects funded by appropriations made to the Air Force, Air Force Reserve, and Air National Guard.

Topics covered

  • Military construction funding
  • Installation Development Plans
  • District Plans
  • Installation Facility Standards
  • Project siting
  • MILCON program execution
  • Construction agent authority

Questions and answers

What financial oversight does AFIMSC/FMAS provide for MILCON?

AFIMSC/FMAS provides oversight and reporting of Air Force MILCON appropriations, allotments, sub-allotments, commitments, obligations, and outlays.

What does AFCEC/CF issue before project design starts?

AFCEC/CF also issues the design instruction to the design manager/construction manager (DM/CM) authorizing the start of project design, and initiates 10 USC § 2807, Architectural and engineering services and construction design, notifications.

When must requests for alternate DoD construction agent authority be identified?

Requests for alternate DoD construction agent authority, to include installation civil engineer squadrons, should be identified early and agreed upon by the proposed and designated DoD construction agents.

What does a District Plan assign to all real property?

All real property is assigned to a district, to include geographically separate sites.

When can a project no longer be re-sited?

Projects will not be re-sited after completion of the 35% design.