452AMWI21-113 — Local Manufacture Procedures

452AMWI21-113 governs local manufacture procedures and the use of locally developed maintenance forms at the 452d Air Mobility Wing.

Search 452AMWI21-113

  • Publication number: 452AMWI21-113
  • Title: LOCAL MANUFACTURE PROCEDURES
  • Date: 2021-12-03

View 452AMWI21-113 on armypubs.army.mil


It assigns Decentralized Materiel Support as the focal point for local manufacture actions and lists the required coordination steps. The checklist covers requests, technical data, materials, approvals, back-shop processing, and parts pickup.

Applies to: This AMWI is applicable to all maintenance personnel assigned to the 452d Air Mobility Wing.

Topics covered

  • Local manufacture requests
  • Locally developed maintenance forms
  • Decentralized Materiel Support
  • Technical order parts breakdowns
  • Quality Assurance approval
  • Back-shop coordination
  • Aircraft parts pickup

Questions and answers

Who is the focal point for local manufacture actions?

Decentralized Materiel Support (DMS) will be the focal point for all local manufacture actions and will provide guidance in the accomplishment of these actions in accordance with applicable AFIs. (paragraph 1)

What must a requester submit for local manufacture coordination?

Submit local man worksheet (approved with this Air Mobility Wing Instruction (AMWI) only) and technical order page of parts breakdown, provide sample, drawings, blueprints, and/or Joint Engineer, Data Management Information Control System (JEDMICS) needed, if applicable to DMS for local manufacture coordination. (paragraph 2)

When is Quality Assurance approval required?

Approval must be obtained through Quality Assurance for all special tools and equipment or any item not coded as local manufacture within the technical order prior to bringing local man worksheet to DMS. (paragraph 2)

What happens if material cannot be obtained through the supply system?

If material is not procurable via supply system, requester must purchase and/or provide material to DMS. (paragraph 2)

What must be specified when the requester provides material?

If requester purchases and/or provides material, they must specify if they want excess material returned. (paragraph 2)

Ask Reggie.Bot a question about 452AMWI21-113