341MWI90-201 — Wing Inspection Team Reception And Support

341MWI90-201 governs reception and support for visiting inspection teams at Malmstrom Air Force Base.

Search 341MWI90-201

  • Publication number: 341MWI90-201
  • Title: WING INSPECTION TEAM RECEPTION AND SUPPORT
  • Date: 2023-01-10

View 341MWI90-201 on armypubs.army.mil


It addresses facilities, equipment, supplies, lodging, transportation, personnel, communications, and security for inspection visits. It sets requirements for arrival coordination, reception workstations, in-briefs, and entry authorization lists.

Applies to: This instruction is applicable to all Air Force personnel assigned or attached to Malmstrom Air Force Base (MAFB).

Topics covered

  • Inspection team reception and support
  • Arrival coordination
  • Reception and in-processing workstations
  • Inspector in-briefs
  • Entry authorization lists

Questions and answers

Who is responsible for the entire reception and support process?

The Project Officer is responsible for the entire reception and support process. (paragraph 3)

Where are the pre-identified main inspection workcenters?

The pre-identified main workcenters are located in building 3080, rooms D100 and B109. (paragraph 2)

How early must the bus and bus driver arrive?

The bus and bus driver will be at the departure location at least 15 minutes prior to departure time. (paragraph 2)

What condition must the reception and in-processing workstation area meet?

The Project Officer for the Reception/In-Processing Workstation Area, in conjunction with the building’s facility manager, will ensure the area is clean and free of any miscellaneous items. (paragraph 5)

How early must in-brief personnel be ready?

The Project Officer for the in-brief will ensure all briefers and support personnel are in place and ready NLT 30 minutes prior to start time. (paragraph 6)

Ask Reggie.Bot a question about 341MWI90-201