TC 3-34.530 governs engineer construction support for planning, building, and making major repair of the Inland Petroleum Distribution System.

Search TC 3-34.530

  • Publication number: TC 3-34.530
  • Title: INLAND PETROLEUM DISTRIBUTION SYSTEM ENGINEER CONSTRUCTION SUPPORT
  • Date: 06/03/2022
  • Proponent: T2COM
  • Status: ACTIVE

View TC 3-34.530 on armypubs.army.mil


TC 3-34.530 covers petroleum supply and distribution, pipeline construction, pump station construction and operation, pipeline filling and testing, and safety. It includes requirements for expansion devices, pump access, strainer cleaning, and cutting and grooving machine operation.

Applies to: TC 3-34.530 applies to the Active Army, Army National Guard/Army National Guard of the United States and United States Army Reserve unless otherwise stated.

Topics covered

  • Inland Petroleum Distribution System
  • Petroleum distribution
  • Pipeline construction
  • Pump station construction and operation
  • Pipeline filling and testing
  • Expansion devices and anchors
  • Strainer assembly operations
  • Cutting and grooving machine safety

Questions and answers

What clothing and protective equipment are required around rotating machinery?

Never wear loose clothing or jewelry around rotating machinery. Always wear gloves, safety glasses, and hearing protectors when operating the cutting and grooving machine. (paragraph 1-5)

When must the cutting and grooving machine be disconnected from power?

Always disconnect the machine from the power supply when mounting or removing the cutting and grooving machine. (paragraph 1-5)

How much pipe deflection is allowed in an expansion device?

At no time should the deflection of the pipe/elbow joints in an expansion device exceed 4-degrees. (paragraph 4-10)

How high above the high-water mark must a pipeline be when crossing a gap?

When installing gap-crossing material, ensure that the bottom of the pipeline is at least 2 feet (60.96-centimeters) above the high-water mark. (paragraph 4-34)

What access must pump stations maintain for pump replacement?

Pumps must be positioned for access to allow for replacement during operation if necessary. (paragraph 5-10)