PAM 12-1 — Security Assistance Procedures And Operations

PAM 12-1 governs the initiation, administration, implementation, and execution of Army security assistance and Foreign Military Sales cases.

Search PAM 12-1

  • Publication number: PAM 12-1
  • Title: SECURITY ASSISTANCE PROCEDURES AND OPERATIONS
  • Date: 03/31/2016
  • Proponent: ASA (AL&T)
  • Status: ACTIVE

View PAM 12-1 on armypubs.army.mil


PAM 12-1 contains processes for pre-letter activities, requests, letters of offer and acceptance, technology security, logistics, training, and financial management. It establishes requirements for case preparation, transportation, congressional notification, security reviews, acquisition, payment schedules, and program execution.

Topics covered

  • Pre-letter of request activities
  • Letters of offer and acceptance
  • Technology security and foreign disclosure
  • Foreign Military Sales acquisition
  • Transportation of materiel
  • Security assistance training
  • Foreign Military Sales financial management
  • Special programs and international activities

Questions and answers

How much of an implementing agency's FMS administrative surcharge funds may be spent on Pre-LOR activities?

An overall 8 percent limit (as a percentage of total FMS administrative surcharge funds allocated to the IA in the same fiscal year) to IA FMS administrative surcharge funds may be expended on Pre-LOR activities. (paragraph 2-1)

What is the purpose of the Pre-LOR process?

The goal of the Pre-LOR process is to assist the international customer in making an informed decision regarding the possible submission of an LOR and to assist the customer in developing an actionable LOR. (paragraph 12-1)

What must accompany a proposed denial of a customer request?

Any proposed denial to a customer request, except those deemed incomplete and irresolvable within the allocated 45 days, will be coordinated with DASA (DE&C). The coordination will include complete justification, along with the relevant background information. (paragraph 2)

When is a transportation plan required for classified materiel?

A transportation plan is required for all shipments of classified material, regardless of the point at which a customer country takes possession of the materiel. (paragraph 5-2)

When must an LOA include a payment schedule?

Unless the initial deposit constitutes the total value of the LOA, each LOA financed under dependable undertaking, cash prior to delivery, FMS credit, Military Assistance Program (MAP), or any combination thereof will include a payment schedule. (paragraph 7-7)