AR 415-16 governs the development, maintenance, use, and governance of the Army Facilities Components System for contingency construction.
View AR 415-16 on armypubs.army.mil
It covers AFCS designs, databases, planning guidance, logistics, construction data, automation, governance, and review. It also establishes authorities and funding provisions for contingency construction, including project limits and notification periods.
AFCS provides readily accessible, current, flexible, adaptable, and scalable standard facility designs that address the initial, temporary, and semi-permanent construction of contingency bases and enable maneuver commanders to plan and execute missions across the full spectrum of operations. (paragraph 4)
The AFCS designs are based on general conditions and requirements anticipated in the JOA and are intended for construction by engineer troops with materials furnished through the Army supply system. (paragraph 4)
Civilian contractors may be used to construct JOA facilities by supplementing the AFCS designs with TOGS. (paragraph 4)
Funding for this section is limited to less than $10 million per year. (paragraph 4)
Projects must have an approved costs of less than $3 million each ($4 million, if the project is solely to correct a life, health, or safety threatening deficiency). (paragraph 4)